Alternative Energy Credits RFP Calendar

 

Activity Date
RFP Addendum Issued and Release of Collateral Requirement Monday, June 13, 2022
Bidder Information Session Wednesday, June 22, 2022
Bidder Qualifications Due (12 p.m.) Wednesday, July 6, 2022
Cure Deficiency Deadline (12 p.m.) Wednesday, July 13, 2022
Qualified Bidders Notified Monday, July 18, 2022
Bid Assurance Collateral and SMA Due (12 p.m.) Friday, July 22, 2022
Bid Proposals Due (12 p.m.) Tuesday, July 26, 2022
PUC Decision Thursday, July 28, 2022
Transaction Confirmations fully executed (2 p.m.) Monday, August 1, 2022
Winning RFP Bidder’s transfer of AECs to PPL Electric Within 5 business days of PUC Decision
Payment by PPL Electric to winning RFP Bidder Within 10 business days of winning RFP Bidder’s transfer of AECs